Services Performed: EPC contract for the interconnection of Campos Novos Substation with Biguaçu and Blumenau Substations Engevix Engenharia and Schahin Engenharia Consortium, under a global price EPC regime. Including design, supervision, management, supply, construction and assembly, consisting of a 525 kV transmission line.

Developer:SC ENERGIA – SANTA CATARINA ENERGY TRANSMISSION COMPANY S / A

Length: 375 Km